The Tejo Project 2018, at Celtejo Pulp Mill, is concerns the installation of a new Recovery Boiler with a thermal power of 217 MWth, a new 40 MWe Condensing Tail Steam Turbine and associated auxiliary systems like Electrical Substations, Condensing Plant, Demineralization Plant and others.
The new Power Plant is designed to meet the future Mill capacity with process steam and electrical power. This Power Plant will also be able to supply and sell electrical power to the national grid
Client: Celtejo
Location: Portugal
Category: Industry